Extract from the Chief Resident Engineer's letter of 30th April, 1909, to the Consulting Engineers.

132

Paragraph 10:-

The negotiations have been completed now for an extension of time on the reclamation Contract and broadly speaking the conditions are as follows. The Government has given an extension of time of twelve months on Contract 29 for the reclamation, also extra works at rates which will give a profit of about $60,000 have been granted while the Contractors are submitting to the penalty being trebled for delay in completion after the twelve months' extension and also a penalty for the non-completion of certain areas of the reclamation which are to be handed over by 1st January, 1910, and for the non-completion of the extra works such as Bridges 2 and 3 and Yau-mati Station which are to be completed by 31st December, 1909, and 31st March, 1910, respectively. Facilities are to be given for running trains through after 1st January, 1910.

Edit History

2026-06-08 03:51:00 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Extract from the Chief Resident Engineer's letter of 30th April, 1909, to the Consulting Engineers. 132 Paragraph 10:- The negotiations have been completed now for an extension of time on the reclamation Contract and broadly speaking the conditions are as follows. The Government has given an extension of time of twelve months on Contract 29 for the reclamation, also extra works at rates which will give a profit of about $60,000 have been granted while the Contractors are submitting to the penalty being trebled for delay in completion after the twelve months' extension and also a penalty for the non-completion of certain areas of the reclamation which are to be handed over by 1st January, 1910, and for the non-completion of the extra works such as Bridges 2 and 3 and Yau-mati Station which are to be completed by 31st December, 1909, and 31st March, 1910, respectively. Facilities are to be given for running trains through after 1st January, 1910.
Baseline (Original)
Extract from the Chief Resident Engineer's letter of 30th. April, 1909, to the Consulting Engineers. 132 է Paragraph 10:- The negotiations have been completed now for an extension of time on the reclamation Contract and broadly speaking the conditions are as follows. The Government has given an extension of time of twelve months on Contract 29 for the reclamation, also extra works at rates which will give a profit of about $60,000 have been granted while the Contractors are submitting to the penalty being trebled for delay in completion after the twelve months' extension and also a penalty for the non-completion of certain areas of the reclamation which are to be handed over by lat. January, 1910, and for the non- -completion of the extra works such as Bridges 2 and 3 and Yau- -mati Station which are to be completed by 31st. December, 1909, and 31st. March, 1910, respectively. Facilities are to be given for running trains through after 1st. January, 1910.
2026-06-08 03:51:00 · Baseline
View content

Extract from the Chief Resident Engineer's letter of 30th.

April, 1909, to the Consulting Engineers.

132

է

Paragraph 10:-

The negotiations have been completed now

for an extension of time on the reclamation Contract and broadly

speaking the conditions are as follows. The Government has given

an extension of time of twelve months on Contract 29 for the

reclamation, also extra works at rates which will give a profit

of about $60,000 have been granted while the Contractors are

submitting to the penalty being trebled for delay in completion

after the twelve months' extension and also a penalty for the

non-completion of certain areas of the reclamation which are

to be handed over by lat. January, 1910, and for the non-

-completion of the extra works such as Bridges 2 and 3 and Yau-

-mati Station which are to be completed by 31st. December, 1909,

and 31st. March, 1910, respectively. Facilities are to be given

for running trains through after 1st. January, 1910.